Financial Associated Press, Dec. 28 - according to the environmental announcement of Chengfa, as of mid December 2021, the accumulated investment of Dengzhou domestic waste incineration power generation project is about 520 million yuan. On December 3, 2021, Chengfa environmental protection energy (Dengzhou) Co., Ltd. held a meeting of the startup and Acceptance Committee of Dengzhou domestic waste incineration power generation PPP project, and the unit entered the complete startup and commissioning. The "72 + 24" hour trial operation of all units was completed on December 26, 2021, with stable equipment operation, good economic indicators and all environmental protection parameters up to standard.